2024 Milling and Resurfacing Project (Park Avenue and St. Paul Street)

Project Description

This is a milling and resurfacing project consisting of the following street segments located in the City of Rochester:

  • Park Avenue (Alexander Street to East Avenue)
  • St. Paul Street (Lowell Street to Riverbank Place)
  • St. Paul Street (Norton Street to Tyler Street)
  • Monroe Avenue at Sumner Park (safety improvements only) 

This project involves milling off the old pavement surface and paving a new surface. Street improvements will also include spot curb and sidewalk replacements, accessible curb ramp replacements, traffic signal and sign improvements, upgrades to catch basins and manhole frames and covers, new pavement markings, bus stop landing pads, minor tree plantings and / or removals, curb bump-outs, and improvements to bicycle and pedestrian facilities. Some improvements may affect existing on-street parking. 

Project Team

  • City of Rochester
  • Monroe County
  • Design Consultant: Barton & Loguidice
  • Contractor: To be determined
  • Construction Inspection: To be determined

Key Stakeholders

Southeast Neighborhood Service Center
Northeast Neighborhood Service Center
14621 Community Rising
Ibero-American Action League
ABC Streets Neighborhood Association
Park Avenue Neighborhood Association
Park Avenue Merchants Association 
Park-Meigs Neighborhood Association
Barrington Street Neighbors
Berkeley Street Neighbors

Public Involvement

Nov. 15, 2023: Park Avenue Public Information Meeting (Public Notice)
Sept. 12, 2023: Park Avenue Public Information Meeting (Public Notice)
Aug. 30, 2023: St. Paul Street Public Information Meeting (Public Notice)

You can find updates on this project at this webpage, as well as through the Instant Input app, available at the Apple App Store or Google Play

Anticipated Project Timeline

Preliminary Design: Spring / Summer 2023
Final Design: Fall 2023 
Bidding and award: Winter 2023 to Spring 2023
Construction: Spring 2024 to Fall 2024 (some work may continue into 2025)

Project Documents

Project Location Maps

Nov. 15, 2023: Park Avenue Public Information Meeting Notes
Nov. 15, 2023: Park Avenue Public Information Meeting Public Notice

Nov. 15, 2023: Park Avenue Public Information Meeting Presentation
Nov. 15, 2023: Park Avenue Public Information Meeting Roll Plots: 
         Alexander Street to Barrington Street
         Edgerton Street to Homer Street
         Homer Street to East Avenue

Sept. 12, 2023: Park Avenue Public Information Meeting Notes
Sept. 12, 2023: Park Avenue Public Information Meeting Presentation

Sept. 12, 2023: Park Avenue Public Information Meeting Roll Plot (DRAFT)
Sept. 12, 2023: Park Avenue Public Information Meeting Public Notice

Aug. 30, 2023: St. Paul Street Public Information Meeting Notes
Aug. 30, 2023: St. Paul Street Public Information Meeting Presentation 

Aug. 30, 2023: St. Paul Street Public Information Meeting Roll Plot (DRAFT)
Aug. 30, 2023: St. Paul Street Public Information Meeting Public Notice

July 21, 2023: Park Avenue Stakeholder Meeting Presentation
July 21, 2023: Park Avenue Stakeholder Meeting Summary

July 12, 2023: St. Paul Street Stakeholder Meeting Presentation
July 12, 2023: St. Paul Street Stakeholder Meeting Summary

Questions?

For questions or comments, please contact:

David Riley, AICP
Project Manager
david.riley@cityofrochester.gov

585-428-6978