2023 Preventive Maintenance Group 1
Project Description:
This project included pavement milling and resurfacing of five streets in the City of Rochester:
- South Avenue (Elmwood Ave to E. Henrietta Rd)
- University Avenue (Culver Rd to Blossom Rd)
- East Avenue (Culver Rd to Probert St)
- Culver Road (Garson Ave to Laurelton Rd)
- Culver Road (Clifford Ave to Norton St)
Improvements also included spot curb and sidewalk repair, spot gutter repair, curb ramp upgrades, adjustment and/or repairs of manholes, receiving basins and water valve castings, minor utility impacts, recommendations for on-street bicycle facilities and parking regulations changes, bus stop landing pads, replacement of traffic loops and pavement markings, and curb bump-outs and mid-block crossings at select locations to improve pedestrian safety.
This project is funded with federal, city and county funds.
Project Documents
- Project Location Map
- Final Design Report – June2022
- Parking Study (February 2022)
- Parking Study (August 2022)
- Public Informational Meeting Notice
- 1st Public Meeting Presentation
- 2nd Public Meeting Presentation
Corridor Maps
(Caution - large files)
- Culver Rd from Clifford Ave to Norton St
- Culver Rd from Garson Ave to Laurelton Rd
- East Ave from Culver Rd to Probert St
- South Ave from E Henriette Rd to Elmwood Ave
- University Ave from Culver Rd to Blossom Rd
Public Involvement
A Public Information Meeting was held on 28, 2022 via Zoom. The presentation can be found in project documents above.
A second Public Information Meeting was held on October 19, 2022 via zoom.
Project Schedule
- Construction: Completed in Fall 2023
For current construction updates, refer to the City’s STREET BEAT website.