River Street Realignment Project
This project includes the realignment of River Street from the CSX crossing to the existing 90 degree bend at 530 River Street, as the final phase of the River Street Extension Project. The project includes, but is not limited to: full-depth pavement, new granite curbs, new catch basins with lateral connections, new shared-use sidewalk (Genesee River Trail connector), new driveway access, new City-owned street lighting system, and streetscape improvements.
Image
Document
Project Team
- City of Rochester
- Monroe County
- Design Consultant: CHA
Anticipated Project Schedule
- Preliminary Design: Completed Spring 2021
- Final Design: Summer to Fall 2021
- Property Acquisition complete 2022
- Bidding and Award: Winter 2022 to Spring 2023
- Construction: Spring 2023 to Fall 2023