Street Name | Project Description | Current Work | Contractor | Expected Completion | Traffic / Parking Restrictions | Project Contact Information |
ALL PUBLIC WORKS PROJECTS | FOR MEDIA INQUIRES: | For all MEDIA INQUIRIES, please contact the City's Communications Bureau at 585-428-7135. | ||||
FOR GENERAL CITY CONSTRUCTION INQUIRES NOT LISTED HEREIN: A&E Bureau Webpage | For public works construction related questions that are not covered in this listing, please contact Andy Wojewodzic, Manager of Construction at 585-428-6523 | |||||
Aqueduct Street (Main St to Bank Place) | This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. | Updated 04/25/25: Final brick paver installation to continue the week of April 28th. Aqueduct closed from E Main St to Race St. | Ramsey Constructors | Spring 2025 | Roadway restrictions for access. Small sections closed daily but access to buildings maintained. | See or call onsite Representative Bill Heselton 585-721-4463, or call Matt Putnam, City Project Manager at 585-428-7494. |
Brooks Avenue (Genesee Park Blvd. to Genesee St.) | Scope: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, sidewalk and curb ramp repairs, and roadway utility adjustments. In addition, new traffic loops, pavement markings, and signs. | Updated 04/25/25: Permanent pavement markings will be completed in summer. | Ramsey Constructors / Nardozzi Companies (Water Work) | Summer 2025 | See or call on site representative Karen Montgomery 585-287-6898, or call 311. | |
Church Street / City Hall (N. Fitzhugh St to Pindle Alley) | This project consists of the replacement of the existing brick sidewalk with new brushed concrete and exposed aggregate sidewalk; replacement of the existing curb including installation of new underdrain, curb access ramp, and milling and resurfacing of Church St. | Updated 04/14/25: Sidewalk closures, pedestrian detours and parking restrictions began on Monday, April 7. | Nardozzi Paving and Construction | Fall 2025 | See or call onsite Representative Jeremy Kimble 585-427-0320 x16, or call Andy Wojewodzic, City Project Manager at 585-428-6523. Field office located at 80 Commercial St, Rochester, NY 14614. | |
Culver Road (Monroe Ave to Atlantic Ave) | Work consists of milling of the existing pavement and placement of a new pavement top course for the entire project corridor. The project also includes miscellaneous fulll depth pavement repairs, replacement of broken or missing curb, hazardous sidewalk section replacement, upgrading sidewalk curb ramps to ADA standards and placement of new pavement markings. | Updated 04/25/2025: City contractor working on sidewalk curb ramps and curb is scheduled to be installed the week of April 28th. Private utilities working throughout the project corridor as well. | Keeler Consruction | Fall 2025 | Daily lane and sidewalk closures and parking restrictions. | See or call on site representative Joe Mancini 585-286-9173, or call Matt Putnam, City Project Manager at 585-428-7494. |
Durand Eastman Park Beach Site Improvements | This project consists of improvements to the park and beach at Durand Eastman Park including trail repair, increased ADA accessibility, and improved beach access. | Updated 04/24/25: Lake Ontario State Parkway Trail is closed from Lot A to Lot C. | TME Excavating Corp. | Summer 2025 | Trail closures | Call Tyler Burke, City Project Manager at 585-428-7571. |
East Main Street (South Avenue to E Main St Bridge) | This project consists of building an addition and envelope repairs to the Rochester Riverside Convention Center. | Updated 04/25/25: Sidewalk and roadway shift in place through Summer of 2026. Pedestrian and Vehicular traffic will be maintained throughout the project. | Javen Construction | Summer 2026 | Main Street lane taken but traffic maintained | See or call onsite Representative Jeff Buzzard 585-319-5341, or call Matt Putnam, City Project Manager at 585-428-7494. Field office located at 16 E Main St, Suite 7, Rochester, NY 14614 |
Exchange Blvd. (Ford St to Basin St) | Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs, and roadway utility adjustments. In addition, new bicycle facilities, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. | Updated 04/25/25: City's contractor is working on Ford St. And Exchange Blvd. Sidewalk closures and temporary parking restrictions will be in place. Milling and Paving are completed on Exchange from Broad St. to Ford St. and Ford St from Exchange to the Roundabout. Work on the intersection of Ford and Exchange has resumed. | Sealand Contractors | Spring 2025 | Daily lane and sidewalk closures and parking restrictions. | See or call on site representative Lisa Barrett 585-363-5085, or call Matt Putnam, City Project Manager at 585-428-7494. |
Fitzhugh Street / City Hall (Church St to Allen St) | This project consists of the replacement of the existing brick sidewalk with new brushed concrete and exposed aggregate sidewalk; replacement of the existing curb including installation of new underdrain, curb access ramp, and milling and resurfacing of Fitzhugh St. | Updated 04/14/25: Sidewalk closures, pedestrian detours and parking restrictions began on Monday, April 7. Contractor continues with sidewalk removals for Phase 1 | Nardozzi Paving and Construction | Fall 2025 | Daily lane and sidewalk closures and parking restrictions. | See or call onsite Representative Jeremy Kimble 585-427-0320 x16, or call Andy Wojewodzic, City Project Manager at 585-428-6523. Field office located at 80 Commercial St, Rochester, NY 14614. |
Genesee Street (Scottsville Road/Elmwood Avenue to Brooks Avenue/South Plymouth Avenue) | Work involves: full depth reconstruction of the existing roadway; water main and water service; new drainage structures; curb; sidewalk; asphalt cycle track; signals; lighting; signing; marking; new trees. | Updated 04/25/25: Sidewalk work to continue the week of April 28th.
One-way detour expected to be in place till end of July 2025. | Ramsey Constructors | Fall 2025 | Daily lane closures and parking restrictions | See or call onsite Representative Bill Heselton 585-721-4463, or call Matt Putnam, City Project Manager at 585-428-7494. Field office located at 1200A Scottsville Rd, Rochester, NY 14624 |
Hazardous sidewalk Replacement North East Phase 1 | Work involves the replacement of heaved and broken sidewalk slabs and restoration of adjacent lawn or driveway areas. | Updated 04/25/24: City's contractor is complete with work in Sectors 3 thru 8. Touch up work to topsoil and seeding is anticipated in the spring. | Espana Enterprises | Spring 2025 | Sidewalks closures on one side of a street at a time while individual slabs are replaced | See or call on site representative Oleg Kaydan 585-645-8277, or call 311. |
Hoeltzer Street (Clinton Ave. to Joseph St.) | Work involves: full depth reconstruction of the existing roadway; storm sewers; curb, pavement; sidewalk; signing; landscaping. | Updated 04/25/25: City's contractor has complete most of the roadway work and is working on driveways, lead walks and drainage adjustments. | Sealand Contractors Corp. | Spring 2025 | Daily lane shifts and parking closures. | See or call on site representative Alex Brownell 585-270-4882, or call 311. |
Park Avenue (Culver Rd to N Goodman St) | Work involves spot curb and sidwalk replacement as well as catch basin installation. | Updated 04/24/25: Contractor is conducting curb and sidewalk work on Culver Rd between Berkeley St and Vassar St. | Villager Construction | Fall 2025 | Daily lane shifts and parking closures. | See or call onsite Representative Roger O'Toole 585-270-4227, or call Matt Putnam, City Project Manager at 585-428-7494. Field Office located at 277 Alexander St, Rochester, NY, 14607. |
Park Avenue (N Goodman St to Alexander St) | Work involves full depth reconstruction of Park Ave between Meigs St and Alexander St. | Updated 04/24/25: Contractor to conduct full depth reconstruction of Park Ave from Meigs St to Alexander St starting 4/7/25. | Villager Construction | Summer 2025 | Park Ave will be one-way only (westbound) from Rowley St to Alexander St. Detour will be in place between Goodman St and Alexander St. | See or call onsite Representative Roger O'Toole 585-270-4227, or call Matt Putnam, City Project Manager at 585-428-7494. Field Office located at 277 Alexander St, Rochester, NY, 14607. |
Pont de Rennes Bridge | Work involves structural repairs, bridge deck replacement, lighting replacement, railing modifications, and landscaping improvements. | Updated 04/24/25: Pont de Rennes Bridge is Open to Pedestrian Traffic Contractor is completing final touchup and site feature installation is ongoing on the bridge. The bridge deck surface will undergo warranty repairs to the epoxy coating. Granite Mills Commons work is under construction with an anticipated completion in mid-summer 2025. | Cold Spring Construction Company | Summer 2025 (Granite Mills Commons) | See or call onsite Representative Dan Frenette 716-442-5840, or call Tomas Andino, City Project Manager at 585-428-6535. Field office located at 80 Commercial St, Rochester, NY 14614. | |
St Paul Street (Norton St to Tyler St) | Work involves milling and resurfacing, spot curb and sidewalk replacement, curb ramp improvements, and adjustment and repair of manholes, catch basins, and water valve castings. | Updated 04/24/25: Paving is complete. Signal improvements remain at the corner of St Paul St and Norton St. | Villager Construction | Summer 2025 | Daily shoulder closures and parking restrictions | See or call onsite Representative Roger O'Toole 585-270-4227, or call Matt Putnam, City Project Manager at 585-428-7494. Field Office located at 277 Alexander St, Rochester, NY, 14607. |
South Avenue (Broad St to Court St) | This project consists of exterior rehabilitation and repair to the exterior masonry envelope of the Rundel Memorial Library. | Updated 4/25/25: Sidewalk and roadway limited to two lanes through end of January 2026. | DGA Builders | Winter 2025 | South Ave restricted to 2 lanes of traffic. | See or call onsite Representative Rene Giannavola 585-333-6475, or call Roseanne Khaleel, City Project Manager at 585-428-6846. Field office located at 50 South Avenue, Rochester, NY 14604. |
South Plymouth Avenue (Genesee St to Ford St) | Work consists of: Milling & resurfacing of asphalt pavement, reconstruction and relocation of curbs & sidewalk, repairs & adjustments to drainage basins, sewer manholes, and water service castings. Surface drainage and ride quality will be improved. | Updated 04/25/25: Milling and paving operations to occur the week of April 28th.
| Ramsey Constructors | Fall 2025 | Daily lane shifts, sidewalk closures and parking restrictions | See or call onsite Representative Karen Mongomery 585-319-4835, or call Matt Putnam, City Project Manager at 585-428-7494. Field office located at 130 West Main St. Suite 210, Rochester, NY 14608 |
State Street (Inner Loop to Lyell Ave | Work consists of: Milling & resurfacing of asphalt pavement, reconstruction and relocation of curbs & sidewalk, repairs & adjustments to drainage basins, sewer manholes, and water service castings. Surface drainage and ride quality will be improved. | Updated 04/25/25: City's contractor working on sidewalk. | Sealand Contractors Corp. | Summer 2025 | Daily lane and sidewalk closures and parking restrictions. | See or call on site representative Lisa Barrett 585-363-5085, or call Matt Putnam, City Project Manager at 585-428-7494. |
Sullivan Street (Clinton Ave. to Joseph Ave.) | Work involves: full depth reconstruction of the existing roadway; storm sewers; curb, pavement; sidewalk; signing; landscaping. | Updated 12/9/24: City's contractor has completed the roadway and is working on final clean up items | Sealand Contractors Corp. | Spring 2025 | Daily lane and sidewalk closures and parking restrictions. | See or call on site representative Alex Brownell 585-270-4882, or call Frank Bonn, City Project Manager at 585-428-8257. |
University Avenue (N. Goodman St to Culver Rd) | Work consists of milling of the existing pavement and placement of a new pavement top course for the entire project corridor. The project also includes miscellaneous fulll depth pavement repairs, replacement of broken or missing curb, hazardous sidewalk section replacement, upgrading sidewalk curb ramps to ADA standards and placement of new pavement markings. | Updated 04/25/2025: City contractor working on the cycle track. Private utilities working throughout project corridor. | Keeler Consruction | Fall 2025 | Daily lane and sidewalk closures and parking restrictions. | See or call on site representative Joe Mancini 585-286-9173, or call Matt Putnam, City Project Manager at 585-428-7494. |
West Main Street (Churchlea Pl to Cascade Dr / West Broad St) | Work consists of: Milling & resurfacing of asphalt pavement, reconstruction and relocation of curbs & sidewalk, repairs & adjustments to drainage basins, sewer manholes, and water service castings. Surface drainage and ride quality will be improved. | Updated 04/25/25: City's contractor to recommence work in early May 2025.
| Ramsey Constructors | Fall 2025 | Daily lane shifts, sidewalk closures and parking restrictions | See or call onsite Representative Karen Mongomery 585-319-4835, or call Matt Putnam, City Project Manager at 585-428-7494. Field office located at 130 West Main St. Suite 210, Rochester, NY 14608 |