Rochester Riverside Convention Center (RRCC) Building Envelope Repairs and Main Street Addition

Image
RTR Ph 2 page header

About the Project

The original 2018 ROC the Riverway Vision Plan conceptualized a small addition on the southeast corner of the Rochester Riverside Convention Center (RRCC), along with terrace and river wall improvements. Throughout the design process, it became apparent that a building addition facing Main Street would have a far greater positive impact for the RRCC due to both the location and amount of expanded event space. The addition will create a modernized and inviting connection to Main Street that will improve local and visitor experiences, leveraging the recently completed Main Street Streetscape Phase II project. The project will include much-needed capital improvements to the existing facility including, but not limited to, a Main Street addition, an LED display panel for RRCC events, landscape planters to replace deteriorated steps, new restrooms within the facility, critical repairs of the exterior building envelope, and site upgrades. Opportunities to achieve additional ROC the Riverway goals, including advancing connectivity along the Genesee River by expansion of the riverfront terrace and trail system to the Broad Street Bridge, will be developed and constructed in parallel with the Aqueduct Reimagined initiative.

Image
Rochester Riverside Convention Center - Design Concept
Rochester Riverside Convention Center - design concept

Project Design 

Stantec Consulting Services Inc., with subconsultants Architectural P.C., Popli Design Group, Lozier Environmental, and Vargas Associates, were selected through the City’s Request for Proposal (RFP) process to provide engineering and design services for the project.  

The project is funded in part by the ROC the Riverway/Upstate Revitalization Initiative administered by Empire State Development.  

Project Schedule

  • Consultant Procurement: Winter 2021
  • Design and Contract Documents: Spring 2021 – Spring 2024
  • Bidding and Award: Spring 2024  Fall 2024
  • Construction Phase: Fall 2024 – Summer 2026

Schedule is subject to adjustment.