South Avenue and Elmwood Avenue Improvement Projecct

About the Project   

The South Avenue and Elmwood Avenue Improvement Project was a City of Rochester and County of Monroe 131K project which consisted of reconstructing two City of Rochester streets.  The project also included a cycle track connection along Elmwood Avenue between the Highland Trail and the Elmwood Cycle Track.  The project is now substantially complete.

  • South Avenue (Elmwood Ave - Bellevue Dr) 
  • Elmwood Avenue (Mt Hope Ave - South Ave)

Project Scope

The projects consists of full depth pavement reconstruction.  Additional improvements will also include new sidewalk, curb, curb ramps, driveway aprons, drainage basins, water main, water services, hydrants, lighting, signals, signing, pavement markings, tree plantings, pedestrian crossing improvements, and bicycle accommodations.

Additional private utility adjustments were made in advance of the construction phase of the project.

Project Documents

Schedule

Preliminary Design    Winter 2019 through Fall 2020
Final Design  Fall 2020 through Fall 2021
Bid and Award  Fall 2021
Construction  Spring 2022 through Fall 2023 

Project Team 

Public Participation

The City hosted a public meeting on July 15, 2021

The City of Rochester presented design options at the NBN6 monthly meeting on February 8, 2021.

The first public informational meeting was held on October 20, 2020.