Farmington Road and Wyand Crescent Rehabilitation

Project Description

This project includes full pavement reconstruction  and/or pavement milling and resurfacing with spot base repair, new granite curbs, spot sidewalk replacement, curb ramp upgrades, new driveway aprons, signage and pavement markings, new water services, adjustment and/or repairs of manholes, receiving basins, and water valve castings, minor street lighting upgrades and minor utility impacts. Speed humps will be replaced on both streets.

  Farmington and Wyand Project Map

This project is funded with City and County funds.

 

Project Team

City of Rochester

Monroe County

Design Consultant: Lu Engineers

Construction Inspection Firm: TBD

Contractor: TBD

 

Key Stakeholders

School #52

 

Project Documents

Project Location Map

Public InformationalMeeting Notice 

Public meeting PowerPoint Presentation

Project Color Rendering  

Public Meeting Minutes

Public Involvement

A Public Information Meeting will be held on Wednesday August 3, 2022 via Zoom Video Webinar.

 

Anticipated Project Schedule

 

  • Preliminary Design: Spring/Summer 2022
  • Final Design:            Summer/Fall 2022
  • Bidding and Award: Winter 2022 to Spring 2023
  • Construction:            Spring 2023 to Fall 2023

 

For current construction updates refer to the City’s STREET BEAT website.

 

Questions?

For questions please contact: 

 

Phoenix Howell

Project Manager

Phoenix.Howell@cityofrochester.gov

585.428.6284