Broadway & South Union Street Improvement Project
About the Project
The Broadway and South Union Street Improvement Project will include, but is not limited to, pavement reconstruction, new curbs, sidewalks, curb ramps, driveway aprons, drainage basins, water main, water services, hydrants, street lighting, signals, signage, pavement markings, tree plantings, and other various streetscape improvements. Bicycle-related improvements, parking regulation changes and a conversion from one-way to two-way travel will be considered.
Image
Public Engagement / Project Documents
A Public Informational Meeting was held on March 20, 2025, at School Without Walls.
Corridor concepts:
Project Schedule
Preliminary Design - Fall 2024 to Summer 2025
Final Design - Fall 2025 to Summer 2026
Construction - Spring 2027 to Fall 2028