Broadway & South Union Street Improvement Project

About the Project 

The Broadway and South Union Street Improvement Project will include, but is not limited to, pavement reconstruction, new curbs, sidewalks, curb ramps, driveway aprons, drainage basins, water main, water services, hydrants, street lighting, signals, signage, pavement markings, tree plantings, and other various streetscape improvements.  Bicycle-related improvements, parking regulation changes and a conversion from one-way to two-way travel will be considered.

Image
Broadway and South Union Street Project Map

Public Engagement / Project Documents

A Public Informational Meeting was held on March 20, 2025, at School Without Walls.

Corridor concepts: 

Project Schedule

Preliminary Design - Fall 2024 to Summer 2025

Final Design - Fall 2025 to Summer 2026

Construction - Spring 2027 to Fall 2028