Street Construction Updates (Street Beat)

 

 Street Name  Project Description Current Work Contractor Expected Completion Traffic / Parking Restrictions Project Contact Information
ALL PROJECTS FOR MEDIA INQUIRES:         For all MEDIA INQUIRIES, please contact the City's Communications Bureau at (585) 428-7135.
ANY CONSTRUCTION FOR GENERAL CITY CONSTRUCTION INQUIRES NOT LISTED HEREIN:         For public works construction related questions that are not covered in this listing, please contact Andy Wojewodzic, Manager of Construction at (585) 428-6523
Aqueduct Street (Main St to Bank Place) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 09/29/23: Private utility work to continue. City's contractor anticipated to start on or about mid-October, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Bank Place (Exchange Blvd to Aqueduct St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 09/29/23: Private utility work has commenced. City's contractor anticipated to begin pouring back sidewalk the week of October 2, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Basin Street (Exchange Blvd to Aqueduct St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 09/29/23:  City's contractor anticipated to continue rebuild of Basin Street the week of October 2, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Basin Street Closed for Several weeks. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Beechwood Neighborhood (Webster Ave to Culver Rd : East Main St to Bay Rd) This project consists of the construction of new ADA curb ramps including new granite curbing, underdrain, concrete, and embedded detectable warning surfaces. New catch basins will be installed at select locations, and other catch basins may receive new frames and grates. 
Updated 09/28/23: Contractor to begin curb ramp excavation, curb replacement and pouring concrete on Parkside, McKinster/Bay, Richland (South) and Ferris (North). 

Project Webpage

Millennium Construction Fall 2023

See or call onsite representative Bill Hughes at (585) 370-9665 or call City Project Manager Frank Bonn at (585) 428-8257.

Field Office located at 1040 N. Winton Rd. 
Brooks Avenue (Genesee Park Blvd. to Genesee St.) Scope: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new  traffic loops, pavement markings, and signs. Updated 9/28/23: City's contractor has resurfaced the roadway, there is an issue with areas of previous water service repairs which have caused depressions in the west bound lane. The City is working with the contractors to solve the problem.  Catch Basins  be adjustment work is ongoing.   

Project Webpage
Ramsey Constructors Fall 2023   See or call on site representative Karen Montgomery (585) 287-6898  , or call Frank Bonn, City Project Manager at (585) 428-8257.
Browns Race (Platt Street to Furnace Street) Work involves: Replacement of stone block pavers, drainage rehabilitation, sidewalk replacement, street lighting replacement, landscaping amenities, and new signage. Updated 9/29/23: City's contractor expected to commence work in late 2023.

Project Webpage
Cold Spring Construction Company Fall 2024   See or call onsite Representative Dan Frenette (716) 442-5840, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 80 Commercial St, Rochester, NY 14614.
Charles Carroll Plaza/Sister Cities Bridge This project consists of the construction of a new pedestrian access connection from the upper level of the Charles Carroll Park Plaza to the existing Sister Cities Bridge and improvements to the lower walkway along the Genesee River.
Updated 09/29/23:  Contractor has begun work on the plaza and sister cities bridge.  Contractor work zone includes the walkway along the Genesee River from Main St to Andrews St.  Access to this area will be restricted until at least winter 2023.  Sidewalk on the south side of Andrews St is closed from State St to St Paul Blvd due to this project.

Project Webpage  

Crane Hogan Structural Services, Ferrauilo Plumbing and Invictus Electrical Fall 2023 Occasional lane closures and parking restrictions on adjacent streets.

See or call on site representative Jeff Buzzard (585) 505-8885, or call Matt Putnam, City Project Manager at (585) 428-7494.
Culver Road (Garson Ave to Laurelton Rd)  Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 09/29/23: Contractor finishing sidewalk restoration and miscellaneous contract items. 

Project Webpage
Keeler Construction      Fall 2023   See or call onsite representative Joe Mancini at (585) 491-4498 or call City Project Manager, Marcus Cox,  at (585) 428-8253.

Field Office located at 311 Alexander Street, Suite 215.
Culver Road (Clifford Ave to Norton St)  Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 09/29/23: Contractor has milled the roadway and is completing roadway repairs. Unforeseen water main break has delayed paving and restoration of the affected area will be done by another contractor. 

Expect traffic delays and lane shifts

Project Webpage
Keeler Construction  Fall 2023   See or call onsite representative Joe Mancini at (585) 491-4498 or call City Project Manager, Marcus Cox,  at (585) 428-8253.

Field Office located at 311 Alexander Street, Suite 215.
East Avenue (Culver Rd to Probert St) Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 09/29/23: Contractor to finish miscellaneous items. 

Project Webpage
Keeler Construction Fall 2023   See or call onsite representative Joe Mancini at (585) 491-4498 or call City Project Manager, Marcus Cox,  at (585) 428-8253.

Field Office located at 311 Alexander Street, Suite 215.
East Main Street (North Goodman St to Culver Rd) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 9/29/23: Punch list work is ongoing.

Project Webpage
Villager Construction Fall 2022 Occasional lane closures and parking restrictions See or call onsite Representative Sid Reedhead (585) 355-4336, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 274 North Goodman St, Room 264 Village Gate, Rochester, NY 14607 
Elmwood Avenue (Mt Hope Ave to South Ave) Work involves: full depth reconstruction of Elmwood Avenue, from Mt. Hope Ave to South Ave, including new water main, drainage structures, curb, pavement, sidewalks, signals, lighting, signing, marking, landscaping and other streetscape enhancements.  Updated 09/29/23:  Minimal construction impacts on Elmwood Ave. Roadwork is mostly complete.

Project Webpage
Sealand Contractors Corp.       Fall 2023 Occasional Lane Closures and parking restrictions      See or call onsite Representative Mike Melino (585) 430-1826, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field Office location 1000 Elmwood Avenue, Suite 300.
Farmington Road (Wyand Crescent to Winton Road)   The scope of work consists of full pavement reconstruction, new granite curbs, spot sidewalk replacement, curb ramp upgrades, new driveway aprons, signage and pavement markings, new water services, repairs of manholes, and new speed humps.  Updated 9/29/23:  Contractor is completing driveway restoration, manhole adjustments, and concrete sidewalks.  Contractor will be installing curb from Whittington Rd. to Presque St.   

Project Webpage
Nardozzi Companies Fall 2023 Daily lane, sidewalk, and parking closures. See or call onsite Representative Jeremy Kimble (585) 427-0320 x16, or call Marcus Cox, City Project Manager at (585) 428-8253.
Furnace Street (Browns Race to Mill Street) Work involves: Replacement of stone block pavers, drainage rehabilitation, sidewalk replacement, street lighting replacement, landscaping amenities, and new signage. Updated 9/29/23: City's contractor expected to commence work in late 2023.

Project Webpage
Cold Spring Construction Company Fall 2024   See or call onsite Representative Dan Frenette (716) 442-5840, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 80 Commercial St, Rochester, NY 14614.
Graves Street (Main St to Race St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 09/29/23: Private utility work to continue. City's contractor anticipated to continue road box out the week of October 2, 2023. 

Project Webpage
Ramsey Constructors Fall 2023 Graves Street Closed for Several weeks starting Monday, August 7, 2023.
See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Hazardous Sidewalk Replacement, Northwest Quadrant, 2023 Phase 4 Repair and replace hazardous sidewalk in sectors 1 & 2, and 21 - 29 of the northeast and northwest quadrants of the City.  Bordered by Clifford Ave.,  Clinton Ave. and the River.  northwest sectors bordered by Ridgeway Ave., West City Line, the Lake and the River.  Updated 9/28/23: This project will replace hazardous sidewalks in the listed sectors.  Work is complete in sector 25  with just driveway and lawn restoration ongoing.  The contractor is now replacing sidewalks in sectors 26 & 27.  

Project Webpage
Espana Construction Fall 2023 Occasional sidewalk closures and possible limited access to driveways.  See or call on site representative John Knapp (585) 370-1794, or call Frank Bonn, City Project Manager at (585) 428-8257.
Jefferson Avenue (Main St. to Champlain St.) Scope involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, spot sidewalk,  curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, pavement markings. Updated 09/29/23: Contractor has finished resurfacing , new pavement markings and adjustments to manholes and catch basins are almost complete.  The white edge lines have been placed to define the new lane layout, MCDOT will be installing the new parking signs.  

Project Webpage
Ramsey Constructors Fall 2023 Daily lane, sidewalk and parking closures. See or call on site representative Karen Montgomery (585) 287-6898  , or call Frank Bonn, City Project Manager at (585) 428-8257.
Mount Hope Cemetery (South Ave. from Fifth Ave to Adlington Ave.) This project consists of road narrowing of South Ave. between Forest Ave. and Second Ave.  The project includes road removal of Fifth Ave. from Elm Ave. to South Ave., South Ave. between Fifth Ave. and Second Ave., and South Ave. between Forest Ave. and Adlington Ave. The contractor will also be conducting curb installation, utility adjustments, and lawn restoration. Updated 9/29/23: Contractor is completing punch list work. Rochester Earth, Inc. Fall 2023 Fifth Ave. is closed from Elm Ave. to South Ave.  South Ave is closed from Fifth Ave. to Adlington Ave. See or call on site representative John Elkins (585) 281-6556, or call Marcus Cox, City Project Manager at (585) 428-8253.
Orange and Saxton Street Work involves: Milling and Resurfacing of the existing roadway; storm sewers improvements; new curb; spot sidewalk replacement; lighting and signage.  Updated 9/28/23:  City's contractor has completed all work.  RG&E and their contractors  are still working on the underground electrical system.  

Project Webpage
Villager Construction, Inc. Fall 2022   See or call on site representative Karen Montgomery (585) 287-6898, or call Frank Bonn, City Project Manager at (585) 428-8257.
Pont de Rennes Bridge Work involves structural repairs, bridge deck replacement, lighting replacement, railing modifications, and landscaping improvements. Updated 9/29/23: City's contractor has begun work on the bridge and Granite Mills Commons.  Structural steel repairs have begun on the bridge superstructure.  Deck removal is ongoing.

Project Webpage

Bridge will be closed to pedestrian traffic from July 5, 2023 through the end of 2024. A pedestrian detour will be posted and maintained throughout construction.  This detour directs traffic across the Smith St/Bausch St bridge.
Cold Spring Construction Company Fall 2024   See or call onsite Representative Dan Frenette (716) 442-5840, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 80 Commercial St, Rochester, NY 14614.
Platt Street (Mill Street to Browns Race) Work involves: Replacement of stone block pavers, drainage rehabilitation, sidewalk replacement, street lighting replacement, landscaping amenities, and new signage. Updated 9/29/23: City's contractor expected to commence work in late 2023.

Project Webpage
Cold Spring Construction Company Fall 2024   See or call onsite Representative Dan Frenette (716) 442-5840, or call Marcus Cox, City Project Manager at (585) 428-8253.

Field office located at 80 Commercial St, Rochester, NY 14614.
Race Street (Graves St to Aqueduct St) This project consists of pavement reconstruction, the installation of curbing, sidewalks, drainage, lighting, landscaping, amenities, signage, and other incidental items. The paved surfaces will be a combination of concrete pavers, cast-in-place concrete, and asphalt. The project will be constructed using phased construction. Updated 09/29/23:  City's contractor anticipated to continue road box out and sidewalk work the week of October 2, 2023.

Road anticipated to open October 9, 2023.

Project Webpage
Ramsey Constructors Fall 2023 Race Street Closed for Several weeks starting Monday, August 7, 2023. See or call onsite Representative Bill Heselton (585) 721-4463, or call Matt Putnam, City Project Manager at (585) 428-7494.

Field office located at 50 South Ave, South Avenue Garage, Rochester, NY 14604  
Reynolds Street (Seward St. to W. Main St.) Scope of work is the installation of Speed Humps and associated signs.  Updated 09/28/2023:  Contractor has  finished installation of Speed Humps.  sign work and pavement marking are mostly complete, remaining new signage will be placed by MCDOT.

Project Webpage
Ramsey Constructors Spring 2023   See or call on site representative Karen Montgomery (585) 287-6898, or call Frank Bonn, City Project Manager at (585) 428-8257
South Avenue (Elmwood Ave to East Henrietta Rd)  Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations. Updated 09/29/23: Contractor to begin construction operations Oct 2nd with sidewalk excavation. 

Project Webpage
Keeler Construction Fall 2023   See or call onsite representative Joe Mancini at (585) 491-4498 or call Marcus Cox, City Project Manager at (585) 428-8253.

Field Office located at 311 Alexander Street, Suite 215.
South Avenue (Elmwood Ave to Bellevue Dr)  Work involves: full depth reconstruction of South Avenue, from Elmwood Ave to Bellevue Drive, including new water main, drainage structures, curb, pavement, sidewalks, signals, lighting, signing, marking, landscaping and other streetscape enhancements.  
Updated 09/29/23: Contractor to restore to binder grade western most lane from Highland to Elmwood Ave. Signal work at Bellevue and Highland is ongoing. Contractor to begin placing asphalt bike paths from Highland to Bellevue. Contractor continuing to pour sidewalks north of Highland Ave. 

Expect delays and new traffic pattern.

Project Webpage

Sealand Contractors Corp.       Fall 2023 Daily lane closures and parking restrictions.  See or call onsite Representative Mike Melino (585) 430-1826 , or call Matt Putnam, City Project Manager at (585) 428-7494.

Field Office location 1000 Elmwood Avenue, Suite 300.
State Street (Basin St to the Inner Loop) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and other streetscape enhancements. Updated 09/29/23: City's contractor is expected to pave the top course of asphalt on the project the week of October 2, 2023.

State Street, (from the Inner Loop to Broad Street), will be one-way for southbound traffic and remain this way through late November 2023. Detour will be posted for north bound travel. 

NOTE: CONSTRUCTION TO CONTINUE TILL THE END OF THE 2023 CONSTRUCTION SEASON. 

Project Webpage
Villager Construction, Inc. Fall 2023  Daily lane closures and parking restrictions See or call on site representative Paul Winterkorn (585) 298-2387, or call Matt Putnam, City Project Manager at (585) 428-7494.
Thurston Road (Genesee Park Blvd. to Arnett Blvd.) Scope: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new  traffic loops, pavement markings, and signs. Updated 9/28/23:   The contractor has  resurfaced the roadway south of Ernestine Street. Work on the new signal at Arnett St. is ongoing.  Paving from Lehigh St. to Arnett Blvd is anticipated to start on 9/29 .

Project Webpage
Ramsey Constructors, Inc. Fall 2023 Occasional lane, sidewalk and parking closures See or call on site representative Karen Montgomery (585) 287-6898  , or call Frank Bonn, City Project Manager at (585) 428-8257.
University Avenue (Culver Rd to Blossom Rd) Work involves: Milling and Resurfacing of existing roadway, spot road base repair, spot curb, gutter, sidewalk and curb ramp repairs,  and roadway utility adjustments. In addition, new bicycle facilities, bus stop landing pads, traffic loops, pavement markings, curb bump outs and mid-block crossings will be installed at select locations.
Updated 09/29/23: Minimal construction impacts to University Ave. Misc. sidewalk repair and final striping remain.

Project Webpage 

Keeler Construction Fall 2023 Occasional lane, sidewalk, and parking closures. See or call onsite representative Joe Mancini at (585) 491-4498 or call City Project Manager, Marcus Cox, City Project Manager at (585) 428-8253.

Field Office located at 311 Alexander Street, Suite 215.
Waring Road (Culver to Norton) Work involves: full depth reconstruction of the existing roadway; water main; storm sewers; curb, pavement; sidewalk; signals; lighting; signing; marking; landscaping; and bicycle facilities.  Updated 9/28/23:   City's contractor has completed all major work, minor  landscape work will continue thru this fall.  

Project Webpage

Ramsey Constructors, Inc. Fall 2022   See  or call onsite Representative Joe Mancini(585) 319-3618, or call Frank Bonn, City Project Manager at (585) 428-8257.
Wyand Crescent (Merchants Road to City Line) The scope of work consists of full pavement reconstruction, new granite curbs, spot sidewalk replacement, curb ramp upgrades, new driveway aprons, signage and pavement markings, new water services, repairs of manholes, and new speed humps. Updated 9/29/23: Contractor is completing sidewalk work from Merchants Rd to the city limit.  Contractor will be completing road boxout north of Farmington Rd during the week of October 2.  

Project Webpage
Nardozzi Companies Fall 2023 Occasional lane, sidewalk, and parking closures. See or call onsite Representative Jeremy Kimble (585) 427-0320 x16, or call Marcus Cox, City Project Manager at (585) 428-8253.